22 Early Supplier Involvement (ESI) in the Design Phase of Construction Projects: Enhancing Efficiency and Sustainability

Manshuk Sabyrova

1. Rationale

The construction industry faces persistent challenges such as cost overruns, project delays, and inefficiencies in material utilization. Traditional procurement approaches tend to involve suppliers only after the design phase, often resulting in costly redesigns, material mismatches, and logistical challenges. Early Supplier Involvement (ESI) presents an alternative strategy that fosters collaboration between designers, contractors, and suppliers at the conceptual and planning stages. By integrating suppliers early, stakeholders can enhance project efficiency, minimize waste, and improve overall sustainability.

ESI is particularly relevant in the modern construction industry, where projects are becoming increasingly complex, requiring seamless integration between various disciplines. Technological advancements such as Building Information Modeling (BIM), artificial intelligence (AI)-driven supply chain analytics, and modular construction techniques further highlight the need for early supplier engagement to optimize project execution. Governments and private-sector stakeholders are increasingly recognizing the value of ESI in promoting sustainability, reducing carbon footprints, and meeting green building standards, making it an essential component of future construction strategies.


2. Research Questions

  • Traditional “design-then-procure” models often force late-stage value engineering, mismatched specifications, and logistical bottlenecks. Our research question—How does involving suppliers early in the design phase construction performance outcomes?—is driven by the need to understand whether ESI can overcome these systemic shortcomings and deliver measurable benefits across project delivery metrics.


3, Data Collection

  • To build a comprehensive understanding of Early Supplier Involvement (ESI) in construction, this case study will combine qualitative interviews and a targeted literature review:

    • Literature Review:
      A focused literature review will be undertaken to examine existing academic and industry publications on ESI, particularly its implementation in construction projects. This review will analyze the definitions, models, benefits, and limitations of ESI, and evaluate documented examples from both peer-reviewed journals and industry reports. It will also highlight the lack of standardized frameworks and case-specific applications, helping to establish the theoretical foundation for the case study.
    • Expert Interview:
      An in-depth, semi-structured interview conducted with a Professor at the University of Washington who specializes in construction management. This interview aims to capture expert insights on the practical implications, challenges, and opportunities related to ESI. As the academic documentation of supplier involvement is often limited or unclear—especially in IPD contexts—the interview helps contextualize the gaps in industry reporting and research.


4. Findings

  • 4.1. The Role of ESI in Enhancing Design EfficiencyThe construction industry has traditionally relied on a sequential project delivery approach where design, procurement, and construction occur in distinct phases. However, studies suggest that integrating suppliers early in the design process significantly reduces design errors and rework (Ajayi & Oyedele, 2018). Suppliers provide valuable input regarding material selection, manufacturing constraints, and cost-efficient design alternatives, which ultimately streamline project execution (Othman & El-Saeidy, 2024).

    Moreover, Building Information Modeling (BIM) has been recognized as a vital tool for enabling early supplier engagement. Studies indicate that BIM facilitates real-time collaboration between designers and suppliers, improving constructability and minimizing clashes during execution (Saunders et al., 2015). The adoption of BIM as part of ESI can enhance visualization, streamline procurement, and optimize design by integrating supplier expertise in the early phases of the project. Despite these benefits, research highlights that resistance to change and lack of standardized policies hinder widespread adoption of ESI in construction projects (Chen, 2010). Furthermore, the fragmentation of construction supply chains complicates coordination, making it challenging to implement ESI effectively (Johnsen, 2009).

    Recent studies highlight that project stakeholders who adopt ESI enhance design quality and avoid last-minute material substitutions that often lead to inefficiencies and cost escalations. Additionally, early collaboration between suppliers and designers contributes to innovative material use, enhanced durability, and better lifecycle performance of building components (Luangcharoenrat et al., 2019).

    Another major benefit of ESI is that it allows for flexible design adaptation during early-stage decision-making. Contractors and suppliers can provide insights on cost-saving measures, alternative material choices, and potential efficiency improvements, ultimately resulting in a more refined project plan (Daoud et al., 2020). These adaptations not only improve financial planning but also ensure that construction remains on schedule with fewer unexpected disruptions.

    4.2. ESI and Supply Chain Optimization

    Effective supply chain management (SCM) in construction plays a crucial role in ensuring the timely delivery of materials while minimizing costs and waste. ESI enables suppliers to provide early input on logistics, lead times, and material standardization, resulting in optimized procurement strategies (Luangcharoenrat et al., 2019). Studies suggest that pre-engineered components reduce material waste, speed up assembly, and lower overall project costs (Othman & El-Saeidy, 2024).

    Furthermore, a significant advantage of ESI is its contribution to modular construction. By involving suppliers early, modular and prefabricated solutions can be integrated into the project, reducing onsite labor requirements, increasing quality control, and improving sustainability. Case studies demonstrate that modular approaches supported by ESI lead to faster project completion and reduced material waste (Daoud et al., 2020). However, a lack of trust and communication barriers between suppliers and project teams remains a common challenge, impeding the full potential of ESI in supply chain integration (Johnsen, 2009).

    Supply chain disruptions have been a major issue in recent years, particularly during global crises such as the COVID-19 pandemic. Research by Daoud et al. (2020) highlights that early supplier involvement helps mitigate supply chain disruptions by fostering proactive procurement strategies and enhancing supplier resilience. Projects that integrate ESI early tend to have more stable supply chain networks and reduced material shortages, leading to smoother project execution and cost savings.

    Moreover, implementing ESI in SCM also enables better waste management. With suppliers involved in the early design stages, excess material use can be reduced, and recyclable, energy-efficient materials can be incorporated into the project (Othman & El-Saeidy, 2024). This leads to enhanced project sustainability, lower environmental impact, and improved compliance with modern green building regulations. Additionally, predictive analytics and supply chain monitoring tools can be incorporated into ESI frameworks to anticipate logistical delays and procurement inefficiencies, further reducing material waste and ensuring optimal resource allocation.

    Furthermore, integrating blockchain technology into SCM frameworks supports transparency in supplier transactions, contract execution, and quality assurance, improving trust between project stakeholders.

    4.3. Risk Mitigation through Early Supplier Engagement

    Risk management is a fundamental concern in construction, where design changes, material shortages, and unforeseen site conditions can cause significant disruptions. Research indicates that ESI helps mitigate project risks by allowing suppliers to identify potential design flaws early, reducing costly changes during construction (Daoud et al., 2020).

    A study by Othman and Elsawaf (2021) found that projects implementing ESI experienced fewer schedule overruns and budget fluctuations. Supplier insights regarding material feasibility and cost implications contribute to more realistic project planning, minimizing uncertainty. Additionally, early engagement with suppliers enhances contractual clarity, reducing the likelihood of disputes and legal conflicts during project execution (Saunders et al., 2015).

    Saunders et al. (2015) further emphasized the role of early supplier engagement in enhancing social sustainability outcomes, particularly in improving worker safety by reducing last-minute design modifications. When suppliers contribute early, safer materials and construction methods can be considered, leading to reduced on-site hazards.

    Another advantage of ESI is reducing financial risks. Since suppliers are involved early, they can offer competitive pricing, reducing the risk of cost overruns associated with sudden material shortages or increased labor costs (Chen, 2010).

    4.4. ESI’s Contribution to Sustainable Construction

    Sustainability has become a central focus in the construction industry as governments and organizations push for greener building practices, reduced carbon footprints, and enhanced resource efficiency. Early Supplier Involvement (ESI) plays a crucial role in sustainable construction by fostering collaboration in the early design stages, optimizing material selection, and integrating environmentally friendly solutions.

    One of the key contributions of ESI to sustainability is material efficiency. By engaging suppliers early, project teams can identify low-carbon materials, recyclable components, and energy-efficient products that minimize waste. Research by Othman & El-Saeidy (2024) indicates that construction projects implementing ESI see a 20-30% reduction in material waste compared to traditional procurement methods. This not only reduces environmental impact but also contributes to cost savings in procurement and waste management.

    Another significant impact of ESI on sustainability is the optimization of construction processes. Modular construction and prefabrication techniques, which rely heavily on early supplier engagement, have been shown to reduce on-site energy consumption and emissions by up to 40% (Luangcharoenrat et al., 2019). When suppliers are involved early, these methodologies can be integrated into the project design, ensuring that sustainability targets are met without compromising structural integrity or cost efficiency.

    Furthermore, ESI enhances supply chain sustainability by promoting local sourcing of materials and reducing the carbon footprint associated with long-distance transportation. By involving suppliers early, procurement strategies can prioritize local manufacturers and sustainable supply chains, leading to a reduction in emissions and logistics costs (Daoud et al., 2020).

    Another benefit of ESI in sustainable construction is the adoption of green building standards and certifications. Many projects that engage suppliers early incorporate materials and designs that align with LEED (Leadership in Energy and Environmental Design), BREEAM (Building Research Establishment Environmental Assessment Method), and WELL Building Standards, ensuring compliance with regulatory and industry benchmarks. Early supplier collaboration facilitates the selection of certified sustainable materials and technologies that contribute to achieving these certifications.

    Lastly, digital tools such as Building Information Modeling (BIM) and Internet of Things (IoT) sensors allow for better tracking and monitoring of resource consumption throughout the construction lifecycle. Suppliers who are engaged early in the design phase can provide insights on optimal material usage, enabling project managers to track and mitigate environmental impacts in real time.

    To enrich the literature review with field perspectives, we interviewed Professor Yong-Woo Kim, a leading expert in Construction Management at the University of Washington. He noted that while ESI fits naturally within IPD’s collaborative ethos, it is rarely formalized in practice. Procurement strategies, he explained, tend to delay supplier selection in favor of competitive bidding. This cultural inertia keeps suppliers at the periphery, limiting their ability to contribute meaningfully to early design. According to Professor Kim, the perception of suppliers as outsiders further complicates integration, despite the alignment of ESI with IPD’s value system. He acknowledged that early supplier engagement can bring advanced material insights and technology to the design phase but cautioned that suppliers might push proprietary solutions that may not align with broader project goals. Most importantly, he emphasized that if project teams intentionally engage suppliers with a sustainability focus, ESI can lead to clear gains in resource efficiency, innovation, and environmental performance.


5. Path Forward: Formalizing ESI in IPD

Our combined analysis of literature and field insight reveals five central findings. First, ESI significantly enhances project outcomes, particularly by improving coordination in the early stages of design. Second, its integration with IPD is conceptually strong but practically limited by the lack of contractual provisions. Third, modular and prefabricated projects stand to gain the most from early supplier input due to their need for precision and off-site coordination.

For ESI to become standard practice, it must be embedded in project contracts and organizational routines. This includes allocating budget for supplier consultation during preconstruction and developing standardized scopes of work that articulate supplier responsibilities. Collaborative technologies such as BIM, AI-driven scheduling, and digital twins can facilitate integration, while pilot projects can help validate the return on investment. Moreover, training programs for both suppliers and design teams can cultivate a shared understanding of how early engagement supports shared project goals. Professor Kim suggested that institutionalizing ESI within IPD frameworks will require cultural and procedural adjustments—most notably in procurement philosophies that value long-term performance over short-term cost savings.


6. Conclusion

The literature reviewed underscores the significant benefits of Early Supplier Involvement (ESI) in the construction industry’s design phase. Research highlights how ESI enhances design efficiency, optimizes supply chains, mitigates risks, and promotes sustainability. However, barriers such as resistance to change, lack of standardized policies, and trust issues between stakeholders hinder full-scale adoption. Future research should explore best practices for ESI implementation, develop strategies to overcome cultural and operational barriers, and investigate policy frameworks that facilitate supplier integration in construction projects.

Additionally, more longitudinal studies are needed to assess the long-term impacts of ESI on project performance, cost savings, and sustainability. Greater industry awareness, targeted training programs, and regulatory incentives could drive wider adoption and integration of ESI as a best practice for modern construction projects.

By leveraging emerging technologies such as artificial intelligence (AI), digital twins, and IoT-enabled procurement platforms, construction firms can maximize the benefits of ESI while addressing logistical inefficiencies and cost variability. These advancements ensure that ESI remains a scalable and adaptable solution for the evolving demands of the global construction industry.

References:

  • Ajayi, S.O., and L.O. Oyedele. “Critical Design Factors for Minimizing Waste in Construction Projects: A Structural Equation Modeling Approach.” Resources, Conservation and Recycling 137 (2018): 302-313.
  • Chen, Y. “Evaluation of Early Supplier Involvement in Product Development.” College of Technology Masters Theses (2010).
  • Daoud, A.O., A.A.E. Othman, O.J. Ebohon, and A. Bayyati. “Overcoming the Limitations of the Green Pyramid Rating System in the Egyptian Construction Industry: A Critical Analysis.” Architectural Engineering and Design Management (2020).
  • Johnsen, T.E. “Supplier Involvement in New Product Development and Innovation: Taking Stock and Looking to the Future.” Journal of Purchasing and Supply Management 15, no. 3 (2009): 187-197.
  • Luangcharoenrat, C., S. Intrachooto, V. Peansupap, and W. Sutthinarakorn. “Factors Influencing Construction Waste Generation in Building Construction: Thailand’s Perspective.” Sustainability 11, no. 13 (2019): 3638.
  • Othman, Ayman Ahmed Ezzat, and Yomna Abdelghany El-Saeidy. “Early Supplier Involvement Framework for Reducing Construction Waste During the Design Process.” Journal of Engineering, Design and Technology 22, no. 2 (2024): 578-597.
  • Saunders, Lance W., Brian M. Kleiner, Andrew P. McCoy, Helen Lingard, Thomas Mills, Nick Blismas, and Ron Wakefield. “The Effect of Early Supplier Engagement on Social Sustainability Outcomes in Project-Based Supply Chains.” Journal of Purchasing & Supply Management 21, no. 3 (2015): 285-295.

 

 


About the author

License

Icon for the Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License

2025 Innovation in the Construction Industry Copyright © 2025 by Prof. Dossick's CM515 Spring 2025 Class is licensed under a Creative Commons Attribution-NonCommercial-NoDerivatives 4.0 International License, except where otherwise noted.